Excavation work for the foundation of the new heating and power plant Will be finished within the next two weeks; base for smokestack (31 feet in diameter and 197 feet tall) is done; railroad siding complete; carpenters installing forms for additional foundation work.
It would require about 22 years ISTC offers a huge variety of courses; it would take twenty-two years for a student to take all of them.