Public Relations News Release — August 16, 1931
| Page | Title | Summary |
|---|---|---|
| 1 | Excavation work for the foundation of the new heating and power plant | Will be finished within the next two weeks; base for smokestack (31 feet in diameter and 197 feet tall) is done; railroad siding complete; carpenters installing forms for additional foundation work. |
| 1 | It would require about 22 years | ISTC offers a huge variety of courses; it would take twenty-two years for a student to take all of them. |